PPOOLEX Test Facility

Condensation studies at LUT started with an open pool test facility (POOLEX) modeling the suppression pool of the BWR containment. During the years 2002-2006, the facility had several modifications and enhancements as well as improvements of instrumentation before it was replaced with a more versatile PPOOLEX facility in the end of 2006.

The PPOOLEX facility consists of a wet well compartment (condensation pool), dry well compartment, inlet plenum and air/steam line piping. An intermediate floor separates the compartments from each other but a route for gas/steam flow from the dry well to the wet well is created by a vertical blowdown pipe attached underneath the floor.

The main component of the facility is the ~31 m³ cylindrical test vessel, 7.45 m in height and 2.4 m in diameter. The vessel is constructed from three separate plate cylinder segments and from two dome segments. The test facility is able to withstand considerable structural loads caused by rapid condensation of steam. The vessel sections modeling dry well and wet well are volumetrically scaled according to the compartment volumes of the Olkiluoto containment buildings. The DN200 (Ø219.1 x 2.5 mm) blowdown pipe is positioned inside the pool in a non-axisymmetric location, i.e. 300 mm away from the centre of the condensation pool. Horizontal piping (inlet plenum) for injection of gas and steam penetrates through the side wall of the dry well compartment. The length of the inlet plenum is 2.0 m and the inner diameter 214.1 mm. There are several windows for visual observation in the walls of both compartments. A DN100 (Ø114.3 x 2.5 mm) drain pipe with a manual valve is connected to the bottom of the vessel. A relief valve connection is mounted on the vessel head. The large removable vessel head and a man hole (DN500) in the wet well compartment wall provide access to the interior of the vessel for maintenance and modifications of internals and instrumentation.

In the plant, there are vacuum breakers between the dry and wet well compartments in order to keep the pressure in wet well in all possible accident situations less than 0.05 MPa above the dry well pressure. In the PPOOLEX facility, the pressure difference between the compartments is controlled via a connection line (Ø114.3 x 2.5 mm) from the wet well gas space to the dry well. A remotely operated valve in the line can be programmed to open with a desired pressure difference according to test specifications. However, the pressure difference across the floor between the compartments should not exceed the design value of 0.2 MPa.

Steam needed in the experiments is produced with the nearby PACTEL [4] test facility, which has a core section of 1 MW heating power and three steam generators. Steam is led through a thermally insulated steam line, made of sections of standard DN80 (Ø 88.9 x 2.0 mm) and DN50 (Ø60.3 x 2.0 mm) pipes, from the PACTEL steam generators towards the test vessel. The steam line is connected to the DN200 inlet plenum with a 0.47 m long cone section. Accumulators connected to the compressed air network of the lab can be used for providing non-condensable gas injection.

© Copyright LUT University